Key dates MUST be updated as programmatic changes are made. Updates can occur outside of Critical Decisions or Baseline Change Proposals.
For FPD Toolbox, Contacts, or PB-K graphs, please see the below links
FPD
Contacts
PB-K
Field Name | Field Requirement | Required at CD-1 |
---|---|---|
CD0 Forecasted Planned Date | Populated at CD-0 | |
CD1 Forecasted Planned Date | Populated at CD-0 | |
CD-2 Forecasted Planned Date | in accordance with CD-1 Approval Doc | X |
CD-3A Forecasted Planned Date (If applicable) | in accordance with CD-1 Approval Doc | X |
CD-3 Forecasted Planned Date | in accordance with CD-1 Approval Doc | X |
CD-4 Forecasted Planned Date | in accordance with CD-1 Approval Doc | X |
Closeout Forecasted Planned Date | Closeout Forecasted Planned Date if known | |
CD3 Lessons Learned Report Received Date | Populated at CD-3 | |
CD4 Lessons Learned Report Received Date | Populated at CD-4 | |
CD4 Preliminary Closeout Report Received Date | Populated at CD-4 | |
Last Peer Review Date | Last Review Date if known |
1. Navigate to https://pars.doe.gov/
2. Click "Projects"
3. Click the "Search for a Project" field and type your project's name of PARS ID.
4. Click "Training Project 1"
5. Click "Key Dates"
6. Click "Edit"
7. Edit the fields by clicking the "mm/dd/yyyy" and selecting the appropraite date.
8. Click "Save".