PLEASE NOTE: All long lead procurement events post CD-3X are entered in PARS as CD-3X events. Capture the key long lead procurement information from the previous CD-3X event in the Notes section of each module. Approval cost must represent the total cost of all long lead procurement events.
For the FPD Toolbox, Contacts, or PB-K graphs, please see the below links
FPD
Contacts
PB-K
Task | Responsibility |
---|---|
DMS Upload > CD-3X Approval Document | FPD, PM |
Project Attributes: Key Dates | FPD, PM |
CD Information: Cost To Go | PM |
CD Information: CD-3X | PM |