Basic Charts |
|
|
|
C-001 |
Not Used |
|
|
C-002 |
DOE Data Validity |
Provides indication of validity and accuracy of EVM data produced by the contractor for management decision making. Focuses on cost data. Concerns apply to project performance and systemic concerns with contractor’s EVMS. |
9/18/2020 |
C-003 |
DOE Schedule Health |
Standard chart with select DQIs on schedule. Good for assessing schedule health, performance, and work-off trend including personnel and work forecasts. |
9/18/2020 |
C-004 |
DOE Variance Analysis |
Includes schedule and cost variance for current and cumulative data, presented in dollars and percent with two y-axis. |
9/18/2020 |
C-005 |
DOE Trend Analysis |
Useful for understanding past and current performance to anticipate future contractor performance. |
9/18/2020 |
C-006 |
DOE Forecast |
Displays if EAC is reasonable and compares independent EAC (IEAC) to contractor’s reported EAC, aiding evaluation of project completion expectations. |
9/18/2020 |
BAC, EAC, ETC |
|
|
|
C-010 |
BAC by CAM |
Breaks down each CAM's percent of budget and dollars in the project. |
12/20/2022 |
C-011 |
BAC by EVM |
Provides budget breakdown by each EV method, including percent of LOE on a project. |
12/20/2022 |
C-012 |
BCWR ETC |
Compares budgeted cost of work remaining to estimate to complete. |
9/18/2020 |
Indices |
|
|
|
C-020 |
Dual Axis - Index vs. Variance |
Compares cost and schedule variances in dollars to cost and schedule variance indices. |
9/18/2020 |
C-021 |
Index Gauge CPI SPI BEI TCPI to EAC |
Shows SPI, Baseline Execution Index (BEI), Current Execution Index, and Completion Index in a gauge format. |
9/18/2020 |
C-022 |
BEI CEI Trend |
Measures efficiency of tasks against baseline and status schedule. |
9/18/2020 |
C-023 |
SPI(t) vs SPI Cum (Use after 65% Complete) |
Compares earned value and earned schedule. Do not use until project is > 65% complete. |
9/18/2020 |
Other Useful Charts |
|
|
|
C-024 |
Earned Schedule - Indices |
Provides earned schedule indices. |
11/10/2020 |
C-025 |
Earned Schedule Duration |
Provides earned schedule duration. |
11/10/2020 |
C-032 |
Labor Rate & Efficiency Variance |
Displays labor rate and efficiency variance. |
8/5/2021 |
C-033 |
OTB Indices |
Displays over target baseline (OTB) indices. |
12/16/2022 |
C-034 |
BCWR by CAM |
Displays budgeted cost of work remaining by CAM. |
12/16/2022 |