1160561 |
Event With Impact |
Does this event task have an impact value on cost and/or schedule? |
risk_task_type = Event & non-zero value found in impact_schedule_min_days, impact_schedule_likely_days, impact_schedule_max_days, impact_cost_min_dollars, impact_cost_likely_dollars, or impact_cost_max_dollars. |
1160562 |
Impact Missing Impact Value |
Is this impact task missing an impact value on cost and/or schedule? |
risk_task_type = Impact & value missing on at least one of impact_schedule_min_days, impact_schedule_likely_days, impact_schedule_max_days, impact_cost_min_dollars, impact_cost_likely_dollars, or impact_cost_max_dollars. |
1160563 |
Likely Impact Cost Dollars Greater Than Max Dollars |
Are the likely impact dollars for cost greater than the max impact dollars? |
impact_cost_likely_dollars > impact_cost_max_dollars. |
1160564 |
Minimum Impact Cost Dollars Greater Than Likely Dollars |
Are the minimum impact dollars for cost greater than the likely impact dollars? |
impact_cost_minimum_dollars > impact_cost_likely_dollars. |
1160566 |
Likely Impact Schedule Days Greater Than Max Days |
Are the likely impact days for schedule greater than the max impact days? |
impact_schedule_likely_days > impact_schedule_max_days. |
1160567 |
Minimum Impact Schedule Days Greater Than Likely Days |
Are the minimum impact days for schedule greater than the likely impact days? |
impact_schedule_minimum_days > impact_schedule_likely_days. |