The following must be completed at CD-1 within the current reporting period.
For Key Dates, FPD Toolbox, Contacts, or PB-K graphs, please see the below links
Key Dates
FPD
Contacts
PB-K
It is acceptable to have multiple requirements in one document, but metadata tags should reflect this case:
Task |
Responsibility |
DMS Upload: CD-1 Approval Document |
FPD, PM |
Project Attributes: Key Dates |
FPD, PM |
Project Attributes: Contacts |
FPD, PM |
CD Information: Cost To Go |
PM |
CD Information: CD-1 |
PM |
If required by DOE Order 413.3B, the final version of the document must be in PARS.
- CD-1 Approval Document
- Analysis of Alternatives Report
- Acquisition Strategy
- Acquisition Strategy Endorsement (Office of PM – MSP only)
- Conceptual Design Report
- Code of Record Documentation
- FPD Appointment Memo
- Project Owner Designation Memo
- Integrated Project Team Charter
- Project Execution Plan (Federal)
- Project Peer Review with Recommendation Status
- Project Management Risk Committee Recommendation
- Risk Management Plan with Risk Register (Contractor)
- Risk Management Plan with Risk Register (Federal)
- Independent Cost Estimate or Independent Cost Review (NNSA-CEPE sufficiency memo - $100M and greater)
- Quarterly/Monthly Project Review
- Design Management Plan (MSP only)
- Funding Profile