UID | Title | Summary | Error Message |
---|---|---|---|
1010008 | WBS ID contained in Title | Is the WBS ID contained in the title? | WBS Titles should not contain the WBS ID. |
1010009 | WBS ID with Adjacent Letters | Does the WBS ID contain letters side by side? | WBS ID contains letters adjacent to one another. |
1010010 | WPM Name Matches CAM | Is the WPM name the same as the CAM name? | WPM name is the same as the CAM name for this WBS |
1010013 | BWC ID Found on CA or WBS | Is there a BWC ID for a WBS element of type CA or WBS? | BWC ID found on WBS element of type CA or WBS |
1010027 | Parent WBS ID Missing From Child WBS ID | Is the Parent WBS ID missing from the Child WBS ID? | Parent WBS ID was not not found in the Child WBS ID. |
1010037 | WP or PP Missing CA Ancestor | Is a CA missing from the ancestry tree of this WP or PP? | WP or PP missing CA ancestry tree |
9010001 | WP or PP Missing EU | Is this WP or PP missing in the WBS EU log? | WBS_ID not in DS17.WBS_ID list where DS01.type = WP or PP. |
9010029 | Subproject ID Missing in Schedule | Is the subproject ID missing in the schedule? | Subproject ID missing in DS04 Schedule |
UID | Title | Summary | Error Message |
---|---|---|---|
1020043 | Narrative Missing | Is the OBS narrative missing? | Narrative is missing. |
9020041 | CA Marked as External | Is this CA marked as external? | CA is marked as external. |
9020046 | OBS ID Missing in DS01 OBS List | Is the OBS ID missing in the DS01 OBS List? | OBS ID is missing in the DS02 OBS ID list. |
UID | Title | Severity | Summary | Error Message |
---|---|---|---|---|
1030046 | Incommensurate Future Budget & Estimates | MINOR | Is there more than a 50% delta between future BCWS & ETC dollars for this chunk of work? (Or, if BCWS is missing, is there at least $1,000 of ETC without BCWSi?) | abs((BCWSi_dollars - ETCi_dollars) / BCWSi_dollars) > .5 (or ETCi_dollars > 1000 where BCWSi = 0) where period_date > CPP_status_date. |
1030063 | CC Found Without CC Description | Is there are CC without an accompanying description? | CC ID found without an accompanying CC description | |
1030066 | Estimates Found A Year or More After Last Recorded Budget | Does this WP or PP show estimates a year or more after the last recorded period of budget? | Last period_date where ETCi <> 0 is twelve or more months after last period_date of BCWSi <> 0 (on Dollars, Hours, or FTEs). | |
1030076 | Negative Actuals | Does this CA, WP, or PP have negative actuals? | CA, WP, or PP found with ACWPi < 0 (Dollars, Hours, or FTEs). | |
1030081 | Budget Missing | Is this WP or PP missing budget? | WP or PP found with BCWSi = 0 (on Dollars, or Hours / FTEs where EOC = Labor). | |
1030085 | 100-0 EVT | Does this work use a 100-0 EVT? | 100-0 EVT (EVT = G) used (This is not recommended). | |
1030088 | Labor Missing Actuals | Is this Labor missing Actual Dollars, Hours, or FTEs? | EOC = Labor with ACWPi <> 0 for either Dollars, Hours, or FTEs, but where at least one other ACWPi = 0. | |
1030089 | Labor Missing Performance | Is this Labor missing Performance Dollars, Hours, or FTEs? | EOC = Labor with BCWPi <> 0 for either Dollars, Hours, or FTEs, but where at least one other BCWPi = 0. | |
1030091 | Labor Missing Estimates | Is this Labor missing Estimated Dollars, Hours, or FTEs? | EOC = Labor with ETCi <> 0 for either Dollars, Hours, or FTEs, but where at least one other ETCi = 0. | |
1030097 | Zero SPAEcum | Is this WBS missing Budget, Performance, Actuals, and Estimates? | Cumulative BCWS, BCWP, ACWP, and ETC are all equal to zero for this piece of work (Dollars, Hours, and FTEs). | |
9030056 | Cost Estimates After PMB End | Is there estimated work after the PMB end? | Period_date of last recorded ETCi (Dollars, Hours, or FTEs) > DS04.ES_Date for milestone_level = 175. | |
9030068 | PP Starting Within 4-6 Months | Is this PP scheduled to start within 4-6 months? | PP with BCWSi > 0 (Dollar, Hours, or FTEs) and period_date within 4-6 months of CPP Status Date. | |
9030070 | Reprogramming Without OTB/OTS Date | Is there BAC, CV, or SV repgrogramming but not OTB/OTS Date? | BAC_rpg, CV_rpg, or SV_rpg <> 0 but without OTB_OTS_Date in DS07 (IPMR Header). | |
9030073 | Cost Periods Found After CD-4 Approved | Are there period dates after CD-4 approved? | Period Dates found after CD-4 approved (DS04.milestone_level = 190). | |
9030095 | Cost Period After PMB End | Is this period date after PMB end? | Period_date > DS04.ES_Date for milestone_level = 175. | |
1030114 | Indirect With Hours and/or FTEs | Does this indirect have hours or FTEs? | EOC = 'Indirect' or is_indirect = 'Y' AND (BCWSi, BCWPi, ACWPi, or ETCi hours or FTEs > 0) |
UID | Title | Summary | Error Message |
---|---|---|---|
1040113 | Task Starts or Finishes after End of PMB | Is this task forecasted to start or finish after the end of the PMB? | ES_date or EF_date is later than the ES_date or EF_Date for the End of PMB milestone (milestone_level = 175). |
1040122 | Task Description Contains Task ID | Does the description contain the task ID? | Description contains task_ID |
1040131 | Soft Constraint Found | Is there a soft constraint on this task? | Soft constraint found (constraint_type = CS_MSOA or CS_MEOA). |
1040136 | Multiple Replanning Milestones In Current Period | Do multiple replanning milestones exist in the current period? | Multiple replanning milestones (milestone_level = 139) found in the current period (ES_date within 35 days of CPP Status Date). |
1040137 | Multiple Reprogramming Milestones In Current Period | Do multiple reprogramming milestones exist in the current period? | Multiple reprogramming milestones (milestone_level = 138) found in the current period (ES_date within 35 days of CPP Status Date). |
1040138 | Actual & Remaining Durations Sum to More Than Original | Do the actual and remaining durations sum to more than the original? | duration_actual_days + duration_remaining_days > duration_original_days. |
1040142 | Actual Start Earlier Than Early Start | Does this task have an Actual Start earlier than the Early Start? (FC) | AS_date < ES_date (FC). |
1040160 | Duplicate CD or BCP Entry | Does this CD or BCP appear more than once in the schedule? | CD or BCP (milestone_level = 1xx) appears more than once in either the FC or BL (or both) (by subproject_ID). |
1040161 | Insufficient Constraint Justification | Is a sufficient justification lacking for the constraint on this task? | Task is lacking a sufficient justification for its constraint (justification_constraint_hard or justification_constraint_soft are lacking at least two words). |
1040164 | Duplicate Description | Is the description for this task duplicated? | Desription is repeated across task IDs (task_ID). |
1040165 | Insufficient Description | Is the task lacking a proper description? | Task is lacking at least two words in its description. |
1040178 | Forecast Task Missing In Baseline | Is this task missing in the baseline schedule? | Task found in forecast schedule (schedule_type = FC) but not in baseline (schedule_type = BL) (by subproject_ID). |
1040183 | Insufficient High Float Justification | Is a sufficient justification lacking for this task with high float? | High float justification was insufficient (lacking at least two words). |
1040184 | High Float Missing Justification (FC) | Is this FC task with high float missing a justification in the forecast schedule? | justification_high_float is blank where task schedule_type = FC and float_total_days > 10% of project remaining duration. |
1040185 | Insufficient Lag Justification | Is a sufficient justification lacking for this task with lag? | Lag justification was insufficient. |
1040189 | LOE Type With Mismatched EVT | Is the LOE type mismatched with the EVT for this task? | Task of type = LOE has a mismatched EVT (EVT should be A or blank). |
1040194 | Insufficient Milestone Level Description | Is a sufficient milestone level description lacking for this milestone? | Milestone is lacking a sufficient milestone level description (at least two words required). |
1040197 | Non-CD or BCP Milestone Missing Description | Is this non-CD or BCP milestone missing a description? | Non-CD or BCP milestone (milestone_level = 138 or 200-800) is missing a description. |
1040201 | Units % Complete Type Utilized | Is this task using a Units % Complete type? | Task uses a Units % Complete type (PC_type = Units). |
1040202 | Planned/Estimated Completion Misaligned with End of PMB | Are the start/finish dates between the Planned/Estimated Completion and End of PMB milestones misaligned? | ES_date & EF_date misaligned between Planned/Estimated Completion and End of PMB milestones (milestone_level = 170 and milestone_level = 175, respectively). |
1040204 | Post-CD3 Project Milestone Not Coded As Finish Milestone | Is this major post-CD3 milestone not coded as a finish milestone? | Post-CD3 milestone (milestone_level = 160 - 800) is not coded as a finish milestone (type = FM). |
1040205 | Pre-CD3 Project Milestone Not Coded As Start Milestone | Is this major pre-CD3 milestone not coded as a start milestone? | Project-level pre-CD3 milestone (milestone_level <= 150) is not coded as a start milestone (type = SM). |
1040211 | Soft Constraint Missing Date | Is this soft constraint missing a constraint date? | Soft constraint found (constraint_type = CS_MSOA or CS_MEOA) missing a constraint_date. |
1040221 | Insufficient WBS Justification | Is a sufficient WBS justification lacking for this task? | Task is lacking a sufficient WBS justification (at least two words required). |
1040228 | BCP Milestones Without Reprogramming | Has a BCP occurred without reprogramming tasks? (FC) | BCP milestone(s) found (milestone_level = 131 - 135) without accompanying RPG tasks (RPG = Y). (FC) |
1040229 | BCP Milestones Without Reprogramming | Has a BCP occurred without reprogramming tasks? (BL) | BCP milestone(s) found (milestone_level = 131 - 135) without accompanying RPG tasks (RPG = Y). (BL) |
1040230 | Soft Constraint Missing Justification | Does this task have a soft constraint without a justification? | Task found with a soft constraint (constraint_type = CS_MSOA or CS_MEOA) but no justification (justification_constraint_soft is null or empty). |
1040321 | CD-4 Early Start or Finish Dates Misaligned Between FC & BL | Are the early start or finish dates for the CD-4 milestone misaligned between FC & BL? | ES_date or EF_date misaligned for CD-4 in the BL & FC schedules (schedule_type = FC & BL). |
1040603 | High Float Missing Justification (BL) | Is this BL task with high float missing a justification in the baseline schedule? | justification_high_float is blank where task schedule_type = FC and float_total_days > 10% of project remaining duration. |
1040604 | Calculated & Original Durations Misaligned | Is the calculated duration substantially different from the original duration? | (EF_days - ES_days) / duration_original_days > .25. |
1040605 | WBS Summary Task | Is this a WBS Summary task? | type = WS. |
9040116 | Quantitative Risk Analysis Confidence Level for Cost Below 95% Following BCP | Is the quantitative risk analysis confidence level for cost below 95% following a BCP? | BCP found (milestone_level = 131 - 135) with quantitative risk analysis confidence level for cost below 95% (DS07.QRA_CL_cost_pct). |
9040129 | Replan or Repgramming Milestone Without OTB/OTS Date | Does this replanning or reprogramming milestone exist without an OTB/OTS Date? | Replan or repgroamming milestone found (milestone_level = 138 or 139) without an OTB/OTS Date (DS07 OTB_OTS_Date). |
9040134 | SVT With Logic | Does this SVT have logic? | SVT (subtype = SVT) task_id found in DS05 task_ID list. |
9040146 | Calendar Name Missing in DS19 (Schedule Calendar STD) | Is this calendar name missing in DS19? | Calendar_name missing in DS19. |
9040148 | CAM Misaligned with DS01 (WBS) | Is the CAM for this task misaligned with what is in DS01 (WBS)? | CAM name does not align with CAM in DS01 (WBS). |
9040187 | LOE Task With Improper Logic | Is this LOE task missing at least one FF and SS predecessor (both discrete)? | DS04.type = LOE or DS04.EVT = A without DS05.type = FF and SS relationships. |
9040203 | Planned/Estimated Completion & End of PMB Delta Misaligned with UB | Is the delta between the Planned/Estimated Completion & End of PMB milestones not equal to UB days? | Delta between Planned/Estimated Completion ES_date (milestone_level = 170) & End of PMB EF_date (milestone_level = 175) <> UB bgt days (DS07.UB_bgt_days). |
9040213 | Non-External SVT | Is this SVT not marked as external in the WBS dictionary (DS01)? | SVT (subtype = SVT) is not marked as external in the WBS dictionary (DS01.external = N). |
9040225 | Non-WP, PP, or SLPP Type Found in Schedule | Is this WBS ID typed as something other than WP, PP, or SLPP in the WBS Dictionary? | WBS_ID is not WP, PP, or SLPP type in DS01.type. |
9040277 | EVT Justification Misaligned With Cost | Is a similar justification for this EVT missing in cost? | EVT Justification found on FC task without a related justification in cost (by WBS_ID). |
9040279 | Reprogramming Missing in CC Log Detail (CA) | Is this Work or Planning Planning with reprogramming missing in the CC Log detail? | WBS_ID where RPG = Y not found in DS10.WBS_ID list (compare by DS01.parent_WBS_ID where parent is of type CA or SLPP). |
UID | Title | Summary | Error Message |
---|---|---|---|
9050280 | Lag Missing Justification | Is the lag for this task missing a justification? | Lag_days <> 0 and lacking a justification in DS04 schedule (justification_lag is null or blank). |
UID | Title | Summary | Error Message |
---|---|---|---|
1060237 | Resource without Budget | Is this resource lacking budget dollars and/or units? | Resource found without budget (budget_dollars and/or budget_units = 0). |
1060239 | Mistyped Labor EOC | Is this Labor EOC mistyped? | Labor EOC (EOC = labor) does not have a type of labor (type <> labor). |
1060246 | Labor Overlap | Is this labor resource scheduled to work on multiple tasks at the same time? | Labor resource start/finish dates overlap across multiple task_IDs. |
1060247 | Duplicate Resource Name | Is this resource name duplicated across resources? | Resource_name repeats across distinct resource_ids. |
1060250 | Resource With Role | Does this resource have a resource ID and a role ID? | Resource item found with both a resource and role ID (resource_ID and role_ID are not blank). |
1060251 | Resource Task without Resource Assigned Starting Soon | Is this task lacking a resource ID planned to start soon (within 3 months)? | Resource item without an ID is planned to start within three months (resource_ID is blank & start_date is within 3 months of CPP SD). |
1060252 | Duplicate Role Name | Is this role name duplicated across roles? | Resource_name repeats across distinct resource_ids. |
9060284 | Resource Performance Misaligned with Cost | Is the performance recorded for this task misaligned with what is in cost (by EOC)? | Resource performance (actual_dollars) <> DS03.BCWPc (BCWPi_dollars) by EOC. |
9060285 | Cost Actuals without Resource Performance (WP) | Are there actuals in cost without performance in resources (by WP WBS & EOC)? | Resource performance (actual_dollars) = 0 even though DS03.ACWPc > 0 (SUM of ACWSi_dollars) by WBS_ID_WP & EOC. |
9060290 | Resource Budgets Misaligned with Cost | Are the resource budget dollars misaligned with what is in cost? | Resource budget_dollars <> cost DB (SUM of DS03.BCWSi_dollars) by WBS_ID & EOC. |
9060293 | Calendar Missing In Standard Calendar List | Is this calendar name missing in the standard calendar list? | calendar_name not found in DS19.calendar_name list. |
9060297 | Resource Remaining Dollars Misaligned with Cost BCWR | Are the resource remaining dollars flowing up to the schedule WBS misaligned with the BCWR in cost (by WBS_ID & EOC)? | Sum of resource remaining dollars rolled up into DS04.WBS_ID do not align with BCWR in DS03 (by WBS_ID & EOC). |
9060298 | Resource Remaining Units Misaligned with Cost BCWR Hours | Are the resource remaining units flowing up to the schedule WBS misaligned with the BCWR hours in cost (by WBS_ID & EOC)? | Sum of resource remaining hours rolled up into DS04.WBS_ID do not align with BCWR hours in DS03 (by WBS_ID & EOC). |
1060267 | Indirect With Hours | Does this indirect resource have hours? | budget, actual, or remaining units > 0 where EOC = Indirect. |
9060304 | Resource Performance without Cost Actuals (CA) | Has this resource recorded performance even though actuals are not recorded in cost (by EOC, at the CA level)? | Resource performance (actual_dollars) > 0 even though DS03.ACWPc = 0 (SUM of ACWSi_dollars) by EOC (CA level). |
9060305 | Resource Performance without Cost Actuals (WP) | Has this resource recorded performance even though actuals are not recorded in cost (by EOC, at the WP level)? | Resource performance (actual_dollars) > 0 even though DS03.ACWPc = 0 (SUM of ACWSi_dollars) by EOC (WP level). |
9060306 | Cost Actuals without Resource Performance (CA) | Are there actuals in cost without performance in resources (by CA WBS & EOC)? | Resource performance (actual_dollars) = 0 even though DS03.ACWPc > 0 (SUM of ACWSi_dollars) by WBS_ID_CA & EOC. |
UID | Title | Summary | Error Message |
---|---|---|---|
1070273 | High or Low Escalation Rate Percent | Is the escalation rate percentage exceptionally low (below 3%) or high (above 20%)? | escalation_rate_pct <= 0.03 or > 0.2. |
1070335 | UB Estimated Greater Than UB Budgeted (Days) | Is the UB estimated days amount greater than UB budgeted? | UB_est_days > UB_est_days. |
1070336 | UB Estimated Greater Than UB Budgeted (Dollars) | Is the UB estimated dollar amount greater than UB budgeted? | UB_est_dollars > UB_est_dollars. |
1070337 | MR Reprogramming | Is there MR reprogramming? | MR_rpg <> 0. |
1070342 | UB Budget Days without UB Budget Dollars | Are there UB budget days but no UB budget dollars? | UB_bgt_days <> 0 & UB_bgt_dollars = 0. |
1070343 | UB Budget without UB Estimate (Days) | Are there UB budget days but no UB estimated days? | UB_bgt_days <> 0 & UB_est_day = 0. |
1070344 | UB Budget Dollars without UB Budget Days | Are there UB budget dollars but no UB budget dayss? | UB_bgt_dollars <> 0 & UB_bgt_days = 0. |
1070345 | UB Budget without UB Estimate (Dollars) | Are there UB budget dollars but no UB estimated dollars? | UB_bgt_dollars <> 0 & UB_est_dollars = 0. |
1070346 | UB Estimated without UB Budget (Days) | Are there UB estimated days but no UB budget days? | UB_est_days <> 0 & UB_bgt_days = 0. |
1070347 | UB Estimated Days without UB Estimated Dollars | Are there UB estimated days but no UB estimated dollars? | UB_est_days <> 0 & UB_est_dollars = 0. |
1070348 | UB Estimated without UB Budget (Dollars) | Are there UB estimated dollars but no UB budget dollars? | UB_est_dollars <> 0 & UB_bgt_dollars = 0. |
1070349 | UB Estimated Dollars without UB Estimated Days | Are there UB estimated dollars but no UB estimated days? | UB_est_dollars <> 0 & UB_est_days = 0. |
1070354 | Zero Profit Fee | Is profit fee zero? | profit_fee_dollars = 0. |
1070356 | Over-Optimistic Cost QRA | Is the quantitative risk analysis confidence level for cost above 95%? | QRA_CL_cost_pct > .95. |
1070358 | Over-Optimistic Schedule QRA | Is the quantitative risk analysis confidence level for schedule above 95%? | QRA_CL_schedule_pct > .95. |
1070362 | Zero Favorable Cost Cum Dollar Threshold | Is the favorable cost cum dollar threshold equal to zero? | threshold_cost_cum_dollar_fav = 0. |
1070363 | Zero Unfavorable Cost Cum Dollar Threshold | Is the unfavorable cost cum dollar threshold equal to zero? | threshold_cost_cum_dollar_unfav = 0. |
1070364 | Zero Favorable Cost Cum Percent Threshold | Is the favorable cost cum percent threshold equal to zero? | threshold_cost_cum_pct_fav = 0. |
1070365 | Zero Unfavorable Cost Cum Percent Threshold | Is the unfavorable cost cum percent threshold equal to zero? | threshold_cost_cum_pct_unfav = 0. |
1070366 | Zero Favorable Cost Inc Dollar Threshold | Is the favorable cost inc dollar threshold equal to zero? | threshold_cost_inc_dollar_fav = 0. |
1070367 | Zero Unfavorable Cost Inc Dollar Threshold | Is the unfavorable cost inc dollar threshold equal to zero? | threshold_cost_inc_Dollar_unfav = 0. |
1070368 | Zero Favorable Cost Inc Percent Threshold | Is the favorable cost inc percent threshold equal to zero? | threshold_cost_inc_pct_fav = 0. |
1070369 | Zero Unfavorable Cost Inc Percent Threshold | Is the unfavorable cost inc percent threshold equal to zero? | threshold_cost_inc_pct_unfav = 0. |
1070370 | Zero Favorable Cost VAC Percent Threshold | Is the favorable cost VAC percent threshold equal to zero? | threshold_cost_VAC_pct_fav = 0. |
1070371 | Zero Unfavorable Cost VAC Percent Threshold | Is the unfavorable cost VAC percent threshold equal to zero? | threshold_cost_VAC_pct_unfav = 0. |
1070372 | Zero Favorable Schedule Cum Dollar Threshold | Is the favorable schedule cum dollar threshold equal to zero? | threshold_schedule_cum_dollar_fav = 0. |
1070373 | Zero Unfavorable Schedule Cum Dollar Threshold | Is the unfavorable schedule cum dollar threshold equal to zero? | threshold_schedule_cum_dollar_unfav = 0. |
1070374 | Zero Favorable Schedule Cum Percent Threshold | Is the favorable schedule cum percent threshold equal to zero? | threshold_schedule_cum_pct_fav = 0. |
1070375 | Zero Unfavorable Schedule Cum Percent Threshold | Is the unfavorable schedule cum percent threshold equal to zero? | threshold_schedule_cum_pct_unfav = 0. |
1070376 | Zero Favorable Schedule Inc Dollar Threshold | Is the favorable schedule inc dollar threshold equal to zero? | threshold_schedule_inc_dollar_fav = 0. |
1070377 | Zero Unfavorable Schedule Inc Dollar Threshold | Is the unfavorable schedule inc dollar threshold equal to zero? | threshold_schedule_inc_Dollar_unfav = 0. |
1070378 | Zero Favorable Schedule Inc Percent Threshold | Is the favorable schedule inc percent threshold equal to zero? | threshold_schedule_inc_pct_fav = 0. |
1070379 | Zero Unfavorable Schedule Inc Percent Threshold | Is the unfavorable schedule inc percent threshold equal to zero? | threshold_schedule_inc_pct_unfav = 0. |
1070380 | CPE Contract Type | Is this a CPE contract type? | type = CPE. |
1070389 | Zero Favorable Cost VAC Dollar Threshold | Is the favorable cost VAC dollar threshold equal to zero? | threshold_cost_VAC_dollar_fav = 0. |
1070390 | Zero Unfavorable Cost VAC Dollar Threshold | Is the unfavorable cost VAC dollar threshold equal to zero? | threshold_cost_VAC_dollar_unfav = 0. |
9070302 | PM EAC Likely Misaligned with Calculated EAC | Is the PM EAC Likely dollars value less than the cost-calculated EAC? | EAC_PM_Likely_dollars < sum of DS03.ACWPc + DS03.ETCc + DS07.UB_est_dollars. |
9070303 | PM EAC Best Date Misaligned with Cost Estimates | Is the PM EAC Best date earlier than the last recorded ETC plus estimated UB? | EAC_PM_best_date < last DS03.period_date where ETCi > 0 (hours, dollars, or FTEs) + DS07.UB_EST_days. |
9070304 | PM EAC Best Date Prior to End of PMB Milestone | Is the PM EAC Best date earlier than the End of PMB milestone? | EAC_PM_Best < minimum DS04.EF_date where milestone_level = 175 (BL or FC). |
9070305 | PM EAC Likely Date Misaligned with Cost Estimates | Is the PM EAC likely date earlier than the last recorded ETC plus estimated UB? | EAC_PM_likely < last DS03.period_date where ETCi > 0 (hours, dollars, or FTEs) + DS07.UB_EST_days. |
9070306 | PM EAC Likely Date Prior to End of PMB Milestone | Is the PM EAC Likely date earlier than the End of PMB milestone? | EAC_PM_Likely < minimum DS04.EF_date where milestone_level = 170 (BL or FC). |
9070307 | PM EAC Likely Date After Contract Completion | Is the PM EAC Likely date later than the Contract Completion milestone? | EAC_PM_Likely_date > minimum DS04.EF_date where milestone_level = 180 (FC only). |
9070310 | RPG without OTB/OTS Date | Are there RPG tasks without an OTB/OTS Date? | DS04 tasks with RPG = Y found without DS07.OTB_OTS_Date. |
9070350 | PM EAC Best Misaligned with Calculated EAC | Is the PM EAC Best dollars value less than the cost-calculated EAC? | EAC_PM_Best_dollars < sum of DS03.ACWPc + DS03.ETCc + DS07.UB_est_dollars. |
9070353 | PM EAC Worst Date Later Than CD-4 | Is the PM EAC Worst date later than the CD-4 milestone date? | EAC_PM_worst_date > DS04.EF_date where milestone_level = 190 (FC only). |
9070362 | EAC PM Likely Incommensurate with WAD BAC | Is the EAC PM likely considerably different from the BAC as reported in the WADs? | |
9070364 | EAC > BAC without OTB / OTS Date | Is EAC greater than BAC without an OTB / OTS date? | DS03.ACWPc + DS03.ETCc > DS03.BCWSc & OTB_OTS_date is missing or blank. |
9070366 | Profit Fee Misaligned With CC Log Detail | Is profit fee misaligned with the dollars delta for profit fee transactions in the CC log detail? | profit_fee_dollars <> sum of DS10.dollars_delta where category = profit-fee. |
UID | Title | Summary | Error Message |
---|---|---|---|
1080398 | WP/PP EOC Comingled (Dollars) | Does this WP/PP WAD have comingled EOCs? | EOC budget dollars > 0 for at least two non-Overhead EOC types, e.g. budget_labor_dollars <> 0 & budget_material_dollar <> 0. |
1080399 | EVT on CA-Level WAD | Is there an EVT for this CA-level WAD? | EVT <> blank or NA & WBS_ID_WP <> blank. |
1080402 | Labor Dollars without Labor Hours | Does this WAD have labor dollars but not labor hours? | budget_labor_dollars > 0 & budget_labor_hours = 0. |
1080403 | Labor Hours without Labor Dollars | Does this WAD have labor hours but not labor dollars? | budget_labor_hours > 0 & budget_labor_dollars = 0. |
1080405 | CAM Authorization After PM Authorization | Is the CAM authorization date later than the PM's? | auth_CAM_date > auth_PM_date. |
1080410 | Missing EVT | Is the EVT missing for this WP/PP-level WAD? | EVT is missing or blank. |
1080411 | Initial Authorization After PM Authorization | Is the initial authorization date for this WAD after the PM date? | initial_auth_date > auth_PM_date (for earliest WAD revision). |
1080412 | Inconsistent Initial Authorization Date | Is the initial authorization date consistent across revisions? | initial_auth_date differs across revisions (by WAD_ID). |
1080418 | Narrative Restates Title | Is the narrative the same as the title? | narrative = title. |
1080428 | Repeat PM Authorization Date Across Revisions | Do multiple revisions share the same PM authorization date? | auth_PM_date repeated where revisions are not the same (by WBS_ID & WBS_ID_WP). |
1080435 | POP Start On or After POP Finish | Is the POP start on or after the POP finish? | pop_start_date >= pop_finish_date. |
1080438 | WPM Authorization Date After CAM Authorization Date | Is the WPM's authorization date later than the CAM's? | auth_WPM_date > auth_CAM_date. |
1080440 | WPM Missing | Is this WPM name missing on this WAD? | WPM is missing or blank where auth_WPM_date found. |
9080429 | POP Finish After Project Planned Completion Milestone (FC) | Is the POP finish later than the planned completion milestone in the forecast scheduel? | pop_finish > DS04.ES_date/EF_date where milestone_level = 170 & schedule_type = FC. |
9080605 | POP Finish Before Forecast Early Finish (CA) | Is the POP finish for this Control Account WAD before the forecast early finish? | pop_finish < DS04.EF_date where schedule_type = FC (by DS08.WBS_ID & DS04.WBS_ID via DS01.WBS_ID & DS01.parent_WBS_ID). |
9080606 | POP Finish Before Forecast Early Finish (WP) | Is the POP finish for this Work Package WAD before the forecast early finish date? | pop_finish < DS04.EF_date where schedule_type = FC (by DS08.WBS_ID_WP & DS04.WBS_ID_WP). |
9080617 | POP Start After Schedule Actual Start (WP) | Is the POP start for this Work Package WAD after the actual start in the forecast schedule? | pop_start > DS04.AS_date where schedule_type = FC (by DS08.WBS_ID_WP & DS04.WBS_ID_WP). |
9080621 | WPM Mismatched With WBS Dictionary | Is the WPM name for this WAD mismatched with what is in the WBS Dictionary? | WPM <> DS01.WPM (by DS08.WBS_ID_WP & DS01.WBS_ID). |
UID | Title | Summary | Error Message |
---|---|---|---|
1090449 | Risk Missing | Are risk IDs missing in the CC log? | Count of CC log entries > 5 & Count of risk_id = 0. |
9090445 | Implementation Date Missing or Unreasonable | Is the implementation date missing or is it considerably after the approved date? | implementation_date is missing or > the next DS03.period_date after the current DS09.approved_date. |
9090448 | Risk Missing in Risk Register | Is this risk ID missing in the risk register? | risk_id missing in DS15.risk_ID list. |
UID | Title | Summary | Error Message |
---|---|---|---|
1100466 | Dollars Delta Missing | Is the dollars delta for this transaction missing or zero? | dollars_delta missing or 0. |
9100469 | OTB/OTS Transactions Misaligned with Cost (CA) | Do the OTB/OTS transaction dollars for this Control Account sum to something other than the BAC reprogramming in cost? | Sum of dollars_delta where category = OTB, OTS, or OTB-OTS <> Sum of DS03.BAC_rpg (by WBS_ID_CA). |
9100470 | OTB/OTS Transactions Misaligned with Cost (WP) | Do the OTB/OTS transaction dollars for this Work Package sum to something other than the BAC reprogramming in cost? | Sum of dollars_delta where category = OTB, OTS, or OTB-OTS <> Sum of DS03.BAC_rpg (by WBS_ID_WP). |
UID | Title | Summary | Error Message |
---|---|---|---|
1110481 | SLPP or PP VAR With Root Cause Narrative | Is there a root cause SV or CV narrative for this SLPP or PP VAR? | narrative_type = 200 or 400 & narrative_RC_SVi, narrative_RC_SVc, narrative_RC_CVi, or narrative_RC_CVc. |
1110484 | CAL ID Missing | Is the CAL ID missing for this VAR? | CAL_ID is missing or blank. |
1110487 | Cost Variance Root Cause Narrative Missing Impact | Is there a cost variance root cause narrative without an impact statement? | narrative_RC_CVi or narrative_RC_CVc found but narrative_impact_cost is blank or missing. |
1110493 | Schedule Variance Root Cause Narrative Missing Impact | Is there a schedule variance root cause narrative without an impact statement? | narrative_RC_SVi or narrative_RC_SVc found but narrative_impact_schedule is blank or missing. |
9110483 | Approved Date Outside Current Period | Is the approved date before the last or after the current status date? | approved_date < DS00.CPP_Status_Date - 1 & approved_date > DS00.CPP_Status_Date. |
9110496 | CV Root Cause Narrative Missing CAL Cost Narrative | Is this CVi or CVc VAR narrative missing a corrective action log entry with a cost narrative? | narrative_RC_CVc or narrative_RC_CVi found without DS12.narrative_cost (by CAL_ID). |
9110497 | SV Root Cause Narrative Missing CAL Schedule Narrative | Is this SVi or SVc VAR narrative missing a corrective action log entry with a schedule narrative? | narrative_RC_SVc or narrative_RC_SVi found without DS12.narrative_schedule (by CAL_ID). |
UID | Title | Summary | Error Message |
---|---|---|---|
1130537 | EAC Dollars > BAC Dollars | Is the EAC greater than the BAC on this subcontract? | EAC_dollars > BAC_dollars. |
9130516 | Actual Finish Misaligned with Forecast Schedule | Is the actual finish date misaligned with the actual finish in the forecast schedule? | AF_date <> DS04.AF_date where schedule_type = FC (by task_ID). |
9130518 | Actual Start Misaligned with Forecast Schedule | Is the actual start date misaligned with the actual start in the forecast schedule? | AS_date <> DS04.AS_date where schedule_type = FC (by task_ID). |
9130522 | BL Finish Misaligned with Baseline Schedule | Is the baseline finish date misaligned with the early finish in the baseline schedule? | BL_finish_date <> DS04.EF_date where schedule_type = BL (by task_ID). |
9130525 | BL Start Misaligned with Baseline Schedule | Is the baseline start date misaligned with the early start in the baseline schedule? | BL_start_date <> DS04.ES_date where schedule_type = BL (by task_ID). |
9130530 | FC Finish Misaligned with Forecast Schedule | Is the forecast finish date misaligned with the early finish in the forecast schedule? | FC_finish_date <> DS04.EF_date where schedule_type = FC (by task_ID). |
9130533 | FC Start Misaligned with Forecast Schedule | Is the forecast start date misaligned with the early start in the forecast schedule? | FC_start_date <> DS04.ES_date where schedule_type = FC (by task_ID). |
UID | Title | Summary | Error Message |
---|---|---|---|
1150548 | Opportunity With Avoid Or Transfer Handling Type | Does this opportunity have an avoid or transfer handling type? | type = O & risk_handling = Avoid or Transfer. |
1150549 | Approved Date After Closed Date | Is the approved date after the closed date? | approved_date > closed_date. |
1150550 | Approved Date After Realized Date | Is the approved date after the realized date? | approved_date > realized_date. |
1150553 | Probability Cost Min % Greater Than Max % | Is the minimum probability cost percent greater than the max percent? | probability_cost_min_pct > probability_cost_max_pct. |
1150554 | Probability Cost Min Between 92 - 98% | Is the minimum probability cost percent between 92 & 98%? | probability_cost_min_pct >= .92 & < .98. |
1150555 | Probability Schedule Min % Greater Than Max % | Is the minimum probability schedule percent greater than the max percent? | probability_schedule_min_pct > probability_schedule_max_pct. |
1150557 | Probability Schedule Min Between 92 - 98% | Is the minimum probability schedule percent between 92 & 98%? | probability_schedule_min_pct >= .92 & < .98. |
1150558 | Realized Date After Closed Date | Is the realized date after the closed date? | realized_date > closed_date. |
9150551 | Risk Closed Before Risk Tasks Have Completed | Is the closed date before all the risk's tasks have finished? | closed_date < FC DS04.EF_date (by DS15.risk_ID & DS16.risk_ID, and DS16.task_ID & DS04.task_ID). |
9150552 | Risk Mitigation Task Missing In Baseline Schedule | Is this risk mitigation task missing in the baseline schedule? | risk_handling = Mitigate & risk_ID not in BL DS04.RMT_ID list. |
UID | Title | Summary | Error Message |
---|---|---|---|
1160561 | Event With Impact | Does this event task have an impact value on cost and/or schedule? | risk_task_type = Event & non-zero value found in impact_schedule_min_days, impact_schedule_likely_days, impact_schedule_max_days, impact_cost_min_dollars, impact_cost_likely_dollars, or impact_cost_max_dollars. |
1160562 | Impact Missing Impact Value | Is this impact task missing an impact value on cost and/or schedule? | risk_task_type = Impact & value missing on at least one of impact_schedule_min_days, impact_schedule_likely_days, impact_schedule_max_days, impact_cost_min_dollars, impact_cost_likely_dollars, or impact_cost_max_dollars. |
1160563 | Likely Impact Cost Dollars Greater Than Max Dollars | Are the likely impact dollars for cost greater than the max impact dollars? | impact_cost_likely_dollars > impact_cost_max_dollars. |
1160564 | Minimum Impact Cost Dollars Greater Than Likely Dollars | Are the minimum impact dollars for cost greater than the likely impact dollars? | impact_cost_minimum_dollars > impact_cost_likely_dollars. |
1160566 | Likely Impact Schedule Days Greater Than Max Days | Are the likely impact days for schedule greater than the max impact days? | impact_schedule_likely_days > impact_schedule_max_days. |
1160567 | Minimum Impact Schedule Days Greater Than Likely Days | Are the minimum impact days for schedule greater than the likely impact days? | impact_schedule_minimum_days > impact_schedule_likely_days. |
UID | Title | Summary | Error Message |
---|---|---|---|
1170573 | EU Justification Missing | Is an EU justification missing for why the min dollars equal the likely, the likel equal the max, or the min equal the max? | justification_EU is missing or blank & EU_min_dollars = EU_likely_dollars, EU_likely_dollars = EU_max_dollars, or EU_max_dollars = EU_min_dollars. |
1170574 | EU Lacking Spread | Are the EU minimum, likely, and maximum dollars all equal? | EU_min_dollars = EU_likely_dollars = EU_max_dollars. |
1170575 | EU Likely Dollars Greater Than Max | Are the EU likely dollars greater than the max dollars? | EU_likely_dollars > EU_max_dollars. |
1170579 | EU Minimum Dollars Greater Than Likely | Are the EU minimum dollars greater than the likely dollars? | EU_min_dollars > EU_likely_dollars. |
1170580 | WBS Time Dependence Inconsistent | Is the time dependent flag inconsistent within this WBS? | time_dependent is not all Y or all N by WBS_ID. |
9170576 | EU Max Dollars Less Than DB | Are the EU maximum dollars less than the cost DB for this WBS_ID / EOC combo? | EU_max_dollars < DS03.DB by WBS_ID_WP & EOC. |
9170577 | EU Max Dollars Less Than EAC (CA) | Are the EU maximum dollars less than the cost EAC (at the CA level)? | EU_max_dollars < DS03.EAC by WBS_ID_CA & EOC. |
9170578 | EU Max Dollars Less Than EAC (WP) | Are the EU maximum dollars less than the cost EAC for this WBS / EOC combo? | EU_max_dollars < DS03.EAC by WBS_ID_WP & EOC. |
9170579 | WBS & EOC Combo Missing in Cost | Is this WBS_ID / EOC combo missing in the cost processor? | Combo of WBS_ID_WP & EOC missin in DS03. |
9170581 | Non-LOE Time Dependence | Is this time dependent WBS non-LOE in cost? | time_dependent = Y & DS03.EVT <> A (by WBS_ID). |
9170583 | WBS Missing in WBS Hierarchy | Is this WBS missing in the WBS hierarchy? | WBS missing in DS01.WBS_ID list. |
9170584 | WBS Of Non-WP or PP Type | Is this WBS of a type other than WP or PP? | WBS_ID not in DS01.WBS_ID where type = WP or PP. |
UID | Title | Summary | Error Message |
---|---|---|---|
1180585 | Schedule EU Justification Missing | Is the EU justification missing to explain why the min EU days equal the likely, the likely equal the max, or the min equal the max? | justification_EU is missing or blank & EU_min_days = EU_likely_days, EU_likely_days = EU_max_days, or EU_max_days = EU_min_days. |
1180586 | Schedule EU Lacking Spread | Are the EU minimum, likely, and maximum days all equal? | EU_min_days = EU_likely_days = EU_max_days. |
1180587 | EU Likely Days Greater Than Max | Are the EU likely days greater than the max days? | EU_likely_days > EU_max_days. |
1180589 | EU Minimum Days Greater Than Likely | Are the EU minimum days greater than the likely days? | EU_min_days > EU_likely_days. |
9180588 | EU Maximum Days Less Than Original Duration | Are the EU maximum days for this task less than the original duration? | EU_max_days < DS04.duration_original_days by schedule_type, task_ID, and subproject_ID. |
9180591 | Schedule EU Task Missing in Schedule | Is this schedule EU task missing in its respective schedule? | task_ID not in DS04.task_ID list (by schedule_type, task_ID, and subproject_ID). |
UID | Title | Summary | Error Message |
---|---|---|---|
1190594 | Shift Exceeds 12 Hours | Are the hours of any of your shifts in excess of 12 hours? | Hours delta between std*##_DDD_shift*#start_time & std##DDD_shift#_stop_time > 12. |
UID | Title | Summary | Error Message |
---|---|---|---|
1200597 | Non-Workday Exception Missing Shift | Is this non-workday exception missing a shift? | exceptionwork_day = N & no exception_shift#start_time or exception_shift#_finish_time found. |
1200598 | Shift Exception In Excess Of 12 Hours | Is this shift exception longer than 12 hours? | Delta between exceptionshift#start_time & exception_shift#_finish_time found > 12. |
9200596 | Calendar Name Missing In Standard Calendar List | Is this calendar missing in the standard list of calendars? | calendar_name not in DS19.calendar_name list. |
UID | Title | Summary | Error Message |
---|---|---|---|
1210599 | Negative Or Zero Rate Dollars | Is the rate negative or zero? | rate_dollars <= 0. |
1210601 | Direct Overhead EOC | Is this Overhead rate typed as direct? | type = D & EOC = Overhead. |
9210602 | Resource & EOC Combo Missing in Forecast Resources | Is this resource EOC missing in the forecast resources? | resource_ID & EOC combo not found in DS06.resource_ID & DS06.EOC (where schedule_type = FC). |